Wiring The Front Connector, Crimp Snap-On Terminals - Siemens SIMATIC S7-400 Hardware And Installation Manual

Hide thumbs Also See for SIMATIC S7-400:
Table of Contents

Advertisement

Wiring the S7-400
4.18

Wiring the Front Connector, Crimp Snap-On Terminals

Procedure
To wire the prepared front connector, follow the steps outlined below:
1. Strip the conductors over approx. 5 mm.
2. Crimp the contacts onto the conductors. You can use a crimping tool which can
be ordered as an accessory for your signal modules.
3. Insert the crimp contacts into the cutouts in the front connector. Start at the
bottom of the front connector.
The order number for crimp contacts can be found in the Reference Manual .
  Â
  Â
  Â
Figure 4-10
4-34
www.gkbpx.com
Wiring a Front Connector with Crimp Snap-On Terminals
S7-400 and M7-400 Programmable Controllers, Installation Manual