Step 6 - Make Final Preparations; Start-Up; Cooling/Heating System - Carrier 42DH 06 Installation, Start-Up And Service Instructions Manual

Horizontal direct drive blower fan coils
Table of Contents

Advertisement

Electric Heater
Wrapper
Step 6 — Make Final Preparations
1.
Power unit(s) off (open unit electrical disconnect) and
install lockout tags on all power supplies to the unit.
2.
Install field-supplied thermostats and perform all other
final wiring needed. Ensure all electrical connections are
secure.
3.
Perform final visual inspection. All equipment, ductwork,
and piping should be inspected to verify all systems are
complete and properly installed and mounted, and that no
debris or foreign articles are left in the unit(s). Clean dirt,
dust, and other construction debris from unit interior.
Assess fan wheel and housing and clean if necessary.
4.
Verify drain line is properly and securely positioned and that
the line is clear. Pour water into drain to verify operation.
5.
Rotate fan wheel by hand to be sure it is free and does not
rub housing.
6.
Install the filter into the filter frame. If field-supplied fil-
ters are used, verify filter size (see Table 4).
Table 4 — Filter Sizes
42DH UNIT
FILTER
SIZE
QUANTITY
06
1
08
1
10
1
12
1
16
2
20/22
2
30
2
7.
Ensure all panels and filters are installed before checking
fan operation. Turn on power to the unit.
8.
Inspect the fan and motor operation.

START-UP

Before beginning any start-up operation, the start-up personnel
shall familiarize themselves with the unit, options and accesso-
ries, and control sequence to understand the proper system op-
eration. All personnel shall have a good working knowledge of
Limit Switch
Knob
Serial Plate
Wiring Diagram
Contactors
(inside the door)
Above is the example of Control box for Size 20 unit with electric heat, disconnect switch and service light.
Fig. 20 — Control Box Layout
NOMINAL FILTER SIZES —
in. (mm)
16
1
/
x 24 (419 x 610)
2
16
1
/
x 24 (419 x 610)
2
18
1
/
x 33 (464 x 838)
4
18
1
/
x 33 (464 x 838)
4
18
/
x 21
/
(464 x 546)
1
1
4
2
20
1
/
x 22 (521 x 559)
2
29 x 22 (737 x 559)
Disconnect Switch
Service Light
Heater Fuses
Strip
Bonded
Ground
Door Switch
Transformer
Terminal Strip
general start-up procedures and have the appropriate start-up
and balancing guides available for consultation.
The building must be completely finished including doors,
windows, and insulation. All internal walls and doors should
be installed. In some cases, the interior decorations and furni-
ture may influence overall system performance. The entire
building should be as complete as possible before beginning
any system balancing.

Cooling/Heating System

Prior to the water system start-up and balancing, flush the
chilled/hot water systems to clean out dirt and debris which
may have collected in the piping during construction. During
this procedure, all unit service valves must be in the closed po-
sition to prevent foreign matter from entering the unit and clog-
ging the valves and metering devices. Strainers shall be in-
stalled in the piping mains to prevent such material from enter-
ing units during normal operation.
During system filling, air venting from the unit is accomplished
by the use of the standard, manual air vent fitting, or the option-
al, automatic air vent fitting installed on the coil (Fig. 21). Man-
ual air vents are basic Schrader valves that could be accessed
from the coil side of the unit and are located between the coil
header and end sheet. To vent the air from the coil, depress the
valve until the air has vented the coil. When water begins to es-
cape through the valve, release the valve.
Automatic air vents may be unscrewed one turn counterclock-
wise to speed initial venting, but should be screwed in for auto-
matic venting after start-up operations.
13
Auxillary Control Box
(supplied when ordered
with 3-speed controls
and/or service light)
Service Light
Battery
24V Control
Fuse
Battery
Charger
Motor
Control
Board
Equipment
Ground
Terminal
Manual Air Vent
Automatic Air Vent
Fig. 21 — Air Vents

Advertisement

Table of Contents
loading

This manual is also suitable for:

42dh 1242dh 1642dh 2042dh 0842dh 3042dh 22 ... Show all

Table of Contents