Boiler Stack Connection - SAS BIO SOLID 19 Operation And Maintenance Manual

Table of Contents

Advertisement

A) the fitting of adjustment feet
1 – adjustment foot with thread
(adjustment range 30 mm)
2 – nut M12
Figure 9 Installation of adjustment feet in a SAS BIO SOLID boilers
The boiler alignment versus the floor is adjusted with a wrench No. 19 and
a bottom setting nut (item 2). When the boiler position versus the floor is finally
set, install the upper nut (item 3) and block the whole set by screwing on the
upper blocking nut (item 2). The wrench No. 19 is not provided with the boiler.
The design of a flue pipe and its connection to the boiler should conform to
the requirements of current national regulations in a country of destination (e.g.,
Minister of Infrastructure Regulation of 12 April 2002, Journal of Laws No. 75).
The boiler should be directly connected to the stack with a smoke connection
in form of a steel pipe, >3 mm thick (of a thermal resistance of >400°C) and of a
diameter allowing its tight connection to the flue outlet and inserting into the chim-
ney. The connection between the flue pipe and the stack must be tightly sealed
(e.g., with high temperature silicone, ceramic sealant, etc.). The pipe should rise
5.3. Podłączenie kotła do komina
in the direction of the stack (min.5°).
Dimensioning and selection of the flue pipe and the connector should be
10)
(np. Rozporządzenie Ministra Infrastruktury z dnia 12.04.2002 Dz.U.Nr 75
performed by a designer holding necessary licences, and the stack system
poz.690 w sprawie warunków technicznych, jakim powinny odpowiadać budynki i ich
should be constructed by a qualified person in accordance with current spe-
usytuowanie).
cific regulations in a country of destination.
The flue pipe to which the central heating boiler will be connected must meet
requirements of current specific regulations of a country of destination (e.g., PN-
-89/B-10425 Smoke, fumes and ventilation ducts, made of bricks. Technical requ-
irements and acceptance tests; Minister of Infrastructure Regulation concerning
technical conditions that should be met by buildings and their setting, of 12 April
2002, Journal of Laws No. 75, item 690, as amended).

7.4. BOILER STACK CONNECTION

B) boiler with feet
3 – washer Ø13
4 – installation opening Ø13 mm
5 – side skid of the boiler
27