7.3
TASKS
System example for the AirCoat procedure
9
Ensure that:
commissioning was carried out in accordance with Chapter 6.7.
1. Visual check:
personal safety equipment, grounding and all devices ready to use.
2. Secure spray gun and insert nozzle into the spray gun.
3. Close return valve (3).
4. Slowly open the ball valve (2).
5. Set required working pressure on the pressure regulator (1).
6. Optimize spray pattern in accordance with the spray gun's operating manual.
7. Start work process.