Requirements

Requirements
Hardware and software requirements:
● An S7-300 station, consisting of a power supply module and a CPU.
● STEP 7 (≥V4.02) is properly installed on your PG. The instructions below, however, are
● You have configured a project for the S7-300 station.
● The PG is connected to the CPU.
● You have an FM 351 module and its configuration package, an external 24 VDC power
● You have installed hardware limit switches and EMERGENCY OFF switches to protect
FM 351 First Steps in Commissioning
Getting Started, 07/2007, A5E01092707-01
only relevant to STEP 7 (V5.0)
supply, an encoder, a drive, and all necessary accessories such as bus connectors, front
connectors and wiring material.