Repeat Fuse Check/Simulated Load Test
If for example the appliance had not been switched ON
the fuse check or simulated load test can be repeated by
selecting Repeat and pressing OK. The fuse check or
simulated load test is then repeated.
Abort Test
If it is decided the appliance is faulty, or a simulated
load test is not possible because the appliance is of a
type that would fail the test, then the Class I, Class II
or Simulated Load tests can be terminated by selecting
Abort and pressing OK.

3.12 Earth Continuity/Insulation Failure

Possible Reasons for Failure other than a faulty
appliance or Lead
Appliance or lead being tested not correctly
u
connected to the HPAT600.
Test probe is not making good contact with the
u
appliance.
Pass levels are not correct for the type of appliance
u
or lead being tested.
Null of the test probe lead resistance incorrect. (Refer
u
to 2.10)
Repeat Test
If for example the test probe was not connected
correctly, the failed test step can be repeated by
selecting Repeat and pressing OK.
Abort Test
If it is decided the appliance or lead is faulty, the test
can be terminated by selecting Abort and pressing OK.
The HPAT600 will display 'FAIL' and the individual
measurement results.