Commissioning steps
12.) Standard setting set on control unit?
13.) Required heating output set in contractor parameter HG04?
14.) Gas type set in contractor parameter HG12?
15.) Check system configuration and modify if required
Contractor parameter HG40
16.) Flue length compensation set according to "Flue length
compensation table" in contractor parameter HG45?
17.) Gas type and heating output entered on label?
18.) Balanced flue system checked?
19.) Flue gas emissions test (emissions test mode):
Gross flue gas temperature
Intake air temperature
Net flue gas temperature
Carbon dioxide content (CO
Carbon monoxide content (CO)
20.) Casing fitted?
21.) Function test carried out?
22.) System user instructed, documentation handed over?
23.) Commissioning confirmed?
3064810_201804
35. Commissioning report
) or oxygen content (O
2
2
Test values or confirmation
Natural gas
LPG
)
_____________
_____________
_____________
(t
- t
A
_____________
_____________
_____________
t
[°C]
A
t
[°C]
A
) [°C]
L
%
ppm
69