MAST BUTT ADAPTER
Drawn
Figure 13.
John Davey
Date
15/7/2008
Scale
• Any extended metal running vertically through the structure should be bonded to the
NTS
lightning downconductor at the top and bottom of the structure.
• Each downconductor should be connected to the earthing system.
• Where practical, all structural steel and metallic reinforcement in the structure should
be bonded to the downconductor system at recommended intervals as per international
standards.
Document 36 II Guardian
Version 1.02
Guardian Install Manual V12.indd 23
MOUNTING BOLT & WASHER
CRIMP LUG
INSULATED STRANDED
COPPER CONDUCTOR
Version
V1.00
Title
CONNECTION OF CONVENTIONAL DOWNCONDUCTORS
TO LPI TERMINALS
File
© Copyright 2008 LPI
MAST BUTT ADAPTER
10mm HOLE DRILLED
THROUGH COPPER TAPE
13mm FROM END
25mm X 3mm
COPPER TAPE
Lightning Protection International Pty Ltd
BC-2.dwg
BC-2