INSTALLATION PROCEDURE

It is recommended that installation is delayed until all building or maintenance work has been completed. If building
work is being carried out in the vicinity of the installation it may result in damage to the panel.
1.
Remove fire panel from its packing and retain the packing for storage of panel parts during installation.
2.
To remove the front – remove two screws located under the bottom edge, pull the bottom edge out then lift
up. Store it face down in the packaging box, taking care of the LED light guides on the back.
3.
Disconnect battery, earth and transformer wires. Remove the 6 * 4mm screws securing the main printed
circuit board from the box. It is essential that once the main PCB has been removed it is stored safely,
observing anti-static precautions. Use the Eurofire packing if no anti-static containers are available. Keep
the 4mm screws in a safe place.
4.
Once the cable entry routes have been decided remove the appropriate knock-outs from the top of the
enclosure. Only use the knockouts near the mains terminal block for mains entry.
5.
Note two 11mm-6mm keyhole slots and two 6mm holes set in dimples are cut in the back of the enclosure.
The enclosure can be securely fixed to the fabric of the building in the following way. Hold the enclosure on
the wall in the desired mounting position and mark the location of the fixing holes. The panel should be
mounted at a height such that the liquid crystal display is at eye level to the user.
6.
Drill and plug wall in the four marked positions then fit enclosure with the appropriate fixing screws.
7.
Feed the required cables into the enclosure then make off a reasonable working length (identify each cable).
Remove any debris from the enclosure. Conduct all insulation tests (note insulation tests must be done with
the detectors and any other electronic devices disconnected from the wiring involved, failure to observe this
could result in severe damage to the electronic parts in the fire panel and associated detectors etc).
8.
Refit control panel PCB taking into account anti-static precautions. Any further insulation tests are prohibited
once the PCB has been re-fitted. Do not terminate cables in the terminals on the control panel PCB.
9.
Fit the two 12 volt batteries in the enclosure but do not connect the batteries into the control panel PCB yet.
IMPORTANT NOTE: The two 12v batteries are connected in SERIES.
10.
Refit the outer lid using the two 4mm screws and contact Emergi-lite Safety Systems to arrange
commissioning of the fire alarm system.
Location of batteries in enclosure.