Setting
Start Direction
Test Sub-Type
Limit Force
Return Force
Cycle Count
Break Threshold
Min Break Threshold
Examples
Force Limit
 Up Speed:
 Down Speed:
 Start Direction:
 Test Sub-Type:
 Limit Force:
The crosshead moves down at 100 mm/min until the applied load is 50 N from tared
zero, once the limit force is reached the test stops.
MultiTest-dV Operating Manual
Options
Choose whether the test direction is upward or downward.
Select the test sub-type (Options are listed above).
Limit and Cyclic Tests Only - Enter the target load for the test.
Cyclic Tests Only - Enter the start load for the test.
Cyclic Tests Only - Enter the number of cycles to be completed.
Move to Break Test Only – Enter the percentage drop from current
maximum load recorded, to activate the break detection.
Example: Current load maximum reading is 1000N, with 80% setting
the load drop must reach 200N before break detection activates.
Move to Break Test Only - Enter the minimum break threshold
(value of load that the test value must rise above for a break
condition to be detected).
AFG must be connected and ON to set this parameter
100 mm/min
100 mm/min
Down
Force Limit
50 N
Mecmesin  35

Hide quick links:

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the MultiTest 1-dV and is the answer not in the manual?

This manual is also suitable for:

Multitest-dv seriesMultitest 2.5-dvMultitest 0.5-dv

Table of Contents