proportional band percentage from the equation below:
Proportional
+ 200
Band
Adjustment
For example:
5. If the controller is used with a control valve, return the control valve to service by slowly opening the upstream and
downstream manual control valves in the pipeline. Close the manual bypass valve, if one is used.
6. Tune the various controller actions.
D Tuning proportional action: Create a load upset by momentarily changing the set point. Check for system
cycling. If the system does not cycle, lower the proportional band setting (thus raising the gain) and disturb the
system again by changing the set point. Continue this procedure until the system cycles. At this point, double
the proportional band setting (proportional band setting X 2).
D Tuning reset action: Disturb the system. If the system does not cycle then speed up the reset by changing the
setting to a lower value (faster reset) and disturb the system again. Continue this procedure until the system
cycles. When the system cycles, multiply the reset time setting by a factor of three (reset time 3) and slow down
the reset by changing the setting to the higher value. The reset is now tuned.
D Tuning rate action: For a controller with rate (4194HC controllers), adjust the rate toward the lowest setting until
cycling occurs. When the system cycles, multiply the rate value by a factor of three (reset time X 3) and slow
down the rate by changing the setting to the higher value. The rate is now tuned.
7. Check the stability of the recommended proportional band setting by introducing a disturbance and monitoring
the process.
8. Once stable control is attained, the process indicator and set point adjustment indicator should be in line. If they are
aligned, return the set point to the desired value. If they are not, readjust the set point to the desired control point
on the process scale and proceed with step 9.
9. If the process indicator is within ±5 percent of the set point indicator, turn the link 3 adjustment (see figure 5‐3 for
location) until the process indicator aligns with the set point indicator. Turn the link 3 adjustment screw clockwise
to increase the process indication or counterclockwise to decrease it. If the process indicator is misaligned with the
set point adjustment by more than ±5 percent of the scale span, perform the calibration procedure for 4194HB and
HC controllers.

Calibration for 4194HB and HC Controllers

WARNING
To avoid personal injury or property damage resulting from the sudden release of pressure, do not exceed the operating
limits given in this manual.

General Calibration Instructions

Note
If the controller has the auto/manual option, be sure the controller is in the automatic mode before performing calibration.
Allowable Overshoot
Pressure Span
200
2 Psig
^ 13%
30 Psig
4194HA, HB, HC Controllers
July 2018
25

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Fisher 4194hcFisher 4194hb

Table of Contents