No.
Part name
Electrical parts
<How to arrange the lead>
Box assembly
Shown in the picture.
(E-box)
Heat exchanger
1) Take off the pipe holder.
(Refrigerant
cycle assembly)
2) Remove screws for heat exchanger.
(4 pcs)
Horizontal 1)
Open a horizontal louver outward and
louver
stretch the arm of louver base same as
the direction in the picture.
Procedure
- 90 -
FILE NO. SVM-18048
Remarks
Louver motor lead
Fan motor lead
Earth-lead from
fan motor base
Damper motor lead
Display unit lead
Pipe holder
Screws for heat
exchanger (4 pcs)