SITE PREPARATION

FIRST STEPS
1
Lay the installation template over plumbing stub-ups and check the position in the operatory.
2
Install air and water shut-off valves (not supplied).
3
Install 4 x 4 electrical connection box.
4
Mark the cabinet mounting points according to the template.
AIR
Pipe: 1/2" n.p.t. Protruding 1" from the floor. Supplied by contractor.
Air supply: pressure 80-100 psi. Air should be free from contaminants.
WATER
Pipe: 1/2" n.p.t. Protruding 1" from the floor. Supplied by contractor.
Water supply: pressure 40-80 psi. Water should be flushed clean before connecting to this equipment.
ELECTRICAL
Electrical: 4 x 4 x 2-1/4" Connection Box with 1/2" conduit knockouts.
Wire box as per local code with top of the box no higher than 4-1/2" above finished floor.
Voltage: 115 VAC, 3 wire, 15 or 20 amp with ground fault circuit interrupter (Series 5 cabinet only).
See "Electrical Outlets" Page 11
CENTRAL VACUUM
Pipe: supplied by contractor. Terminated with 5/8 OD tube protruding 1" from the finished floor.
GRAVITY DRAIN
Pipe: 5/8" OD tube protruding 1" from the floor. Place trap in-line and use vented fitting to conform to local codes.
Supplied by contractor.
WARNING: Ensure the cabinet is
properly grounded to protective earth.
CAUTION: Electrical utilities must be installed according to local codes and by a licensed electrician.
SERIES 4 & SERIES 5 12 O'CLOCK CABINET
WARNING: 3rd party x-ray systems must be
connected to a dedicated electrical circuit.