Running Environment Check

Engineering wastes must be cleaned. After the installation is
finished, the work site should be recovered to what it was,
without any cable strap, stub, waste paper box, waste cable or
waste plastic bag. The whole site must be clean and tidy.

Other Environment Check

During the installation, record the relevant information according
to the base station information table in the installation
acceptance report.

Power-on and Power-off Test

This section describes the Power-on and Power-off procedures at
first time.

Power-On Procedure

The following describes prerequisites and procedure of power-on
ZXMBW E9200 equipment.
Prerequisites
Steps
1. The ZXMBW E9200 cabinet has no power switch. Enable the
2. If any exception occurs during the power-on, disconnect the
E

Power-Off Procedure

Disconnect the external power switch.
42
Confidential and Proprietary Information of ZTE CORPORATION
The voltage of the power supply meets the requirement of
the ZXMBW E9200
The cabinet power and the grounding cable are correctly
connected.
The cabinet power plug is disconnected from the power
socket.
external power switch to power on the cabinet.
switch or remove the power plug. Find out the cause.
.
ND OF STEPS