2. Go on pulling the bracing cord until the tower stands upright. Separate the working cord and fix
it on its anchor.
3. Check and adjust the strain of each fixed wire cable. Over tight force may bend the tower while
over loose force may cause the tower unstable and shakable. The perfect force is neither too
loose nor too tight and can be adjusted through circumrotating the bolt.
Installation specification of taper tower
Step 1: Choosing installation sites
Please refer to the installation specification of guyed tower (Step 1)
Step 2: Concrete the base
Refer to the following graphs according to the different product model. Special attention should
be paid to the consistent between anchor and the opening of tower base.