Mira Coda PRO ERD Installation & User Manual page 6

Thermostatic bar valve
Table of Contents

Advertisement

Installation
1. Install the pipework making sure that it is level and set the correct distance apart (150 mm) by using the
supplied plastic pipe guide.
Important!
1.1 Pipes must be left a minimum of 50 mm long in front of the wall surface.
1.2 Connections are: Hot-Left, Cold-Right. This is very important as the Mira Coda Pro does not
allow for reversed inlets.
1.3 Pipes must be straight and at 90° to the finished wall surface.
150
Pipe Centres in Wall
HOT
2. Fit the plastic pipe guide over the inlet pipes to
hold them in position.
3. Leave the plastic pipe guide in place and finish
the wall.
COLD
6
50 mm Minimum
Plastic Pipe Guide
Inlet Pipes