Sanyo Mini ECO-i 85464359981002 Installation Instructions Manual page 66

Sanyo air conditioner installation instructions
Table of Contents

Advertisement

(3) Do a leak test of all joints of the tubing (both indoor and
outdoor) and both gas tube and liquid tube service
valves. Bubbles indicate a leak. Wipe off the soap with a
clean cloth after the leak test.
(4) After the system is found to be free of leaks, relieve the
nitrogen pressure by loosening the charge hose
connector at the nitrogen cylinder. When the system
pressure is reduced to normal, disconnect the hose from
the cylinder.
Evacuation
(1) Attach the charge hose end described in the preceding
steps to the vacuum pump to evacuate the tubing and
indoor unit. Confirm that the "Lo" knob of the manifold
valve is open. Then, run the vacuum pump. The
operation time for evacuation varies with the tubing
length and capacity of the pump. The following table
shows the amount of time for evacuation:
Required time for evacuation
when 30 gal/h vacuum pump is used
If tubing length is
less than 49 ft.
45 min. or more
NOTE
The required time in the above table is calculated based on
the assumption that the ideal (or target) vacuum condition is
less than –14.7 psig (–755 mmHg, 5 Torr).
(2) When the desired vacuum is reached, close the "Lo"
knob of the manifold valve and turn off the vacuum pump.
Confirm that the gauge pressure is under –14.7 psig
(–755 mmHg, 5 Torr) after 4 to 5 minutes of vacuum
pump operation.
If tubing length is
longer than 49 ft.
90 min. or more
66
Manifold valve
Pressure
Lo
Hi
gauge
Vacuum pump
Open
Gas
tube
Open
Liquid
tube
Fig. 7-4
Service port ø5/16"
Close
Outdoor unit
Close