6.9 Mounting Transducers into the MCF

To maintain ATEX certification the transducer face must be protected against impact. Protection is
IMPORTANT:
provided by properly installing the transducer into the clamping fixture. Care must be taken during
installation to ensure that protection is provided.
The last installation step is mounting the transducers into the clamping fixture. To mount the transducers into the GCF,
complete the following steps:
1. Apply a thread sealant to the transducer threads. A sealant is not required for installations in the USA, but a sealant
must be used for installations in EU countries.
2. Before mounting the transducers into the MCF, thread the electrical junction box onto the BNC connector end of
the transducer. Make sure that at least five full threads are engaged. Be sure to orient the cover of the junction box
so it is accessible to make cable connections after the transducer is installed.