Checking The Power Supply; Energizing The Ied; Checking The Ied Operation - ABB RER670 Commissioning Manual

Relion 670 series, railway application version 2.2 iec
Hide thumbs Also See for RER670:
Table of Contents

Advertisement

Section 4
Starting up
4.3
4.4
4.4.1
34
Three-phase test kit or other test equipment depending on the complexity of
the configuration and functions to be tested.
PC with PCM600 installed along with the connectivity packages
corresponding to the IEDs to be tested.
Administration rights on the PC, to set up IP addresses
Product documentation (engineering manual, installation manual,
commissioning manual, operation manual, technical manual and
communication protocol manual)

Checking the power supply

Do not insert anything else to the female connector but the
corresponding male connector. Inserting anything else (such as a
measurement probe) may damage the female connector and prevent
a proper electrical contact between the printed circuit board and the
external wiring connected to the screw terminal block.
Check that the auxiliary supply voltage remains within the permissible input
voltage range under all operating conditions. Check that the polarity is correct
before energizing the IED.

Energizing the IED

Checking the IED operation

Check all connections to external circuitry to ensure correct installation, before
energizing the IED and carrying out the commissioning procedures.
Energize the power supply of the IED to start it up. Keep the DC power supply on
until the Root menu or the selected default screen is shown on the HMI before
interrupting the DC power supply again. The energization could be done in a
number of ways, from energizing a whole cubicle with many IEDs to energizing
each single IED one by one.
If HW (i.e. I/O and/or communication boards etc.) have been changed (i.e.
removed, replaced, or added), the user should re-configure the IED by navigating
in the local HMI menu to: Main menu/Configuration/Reconfigure HW modules
to activate the changed hardware modules in order to enable the self-supervision
function to detect possible hardware errors.
Check also the self-supervision function in Main menu/Diagnostics/IED status/
General menu in local HMI to verify that the IED operates properly.
Set the IED time if no time synchronization source is configured.
1MRK 506 377-UEN C
Railway application RER670 2.2 IEC
Commissioning manual
M11725-2 v6
M11726-2 v8