3 PRE-INSTALLATION PREPARATION AND GUIDELINES
NOTE: Before installing unit, determine whether any building alterations are required to run piping,
wiring and ductwork. Follow all unit dimensional drawings and refer to the submittal engineering
dimensional drawings of individual units for proper clearances.
Refer to Table B.2 on page 100, or Table B.4 on page 104, and submittal drawings to determine the type
of system being installed and anticipate building alterations, piping and ductwork needed.
The unit dimensions, pipe-connection locations, and piping schematics are described in the submittal
documents included in the
Verify that the floor is level, solid and sufficient to support the unit. See Table 3.3 on page 20
for unit weights.
Confirm that the room is properly insulated and has a sealed vapor barrier.
For proper humidity control, keep outside or fresh air to an absolute minimum (less than 5% of
total air circulated in the room).
Do not install a Liebert PDX/PCW in an alcove or at the end of a long, narrow room.
Install the units as close as possible to the largest heat load.
Allow at least the minimum recommended clearances for maintenance and service. See the
appropriate submittal drawings for dimensions.
We recommend installing an under-floor water detection system. Contact your Vertiv™
representative for information.
Vertiv | Liebert® PDX™ and PCW™ Installer/User Guide |
Submittal Drawings
on page 106.
17

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Pw011Px011Px029Px023Pw017Pw029

Table of Contents