CONTROL BOARD REPLACEMENT INSTRUCTIONS
To access to "tS" parameter:
A. Press and hold Reset button for 10 seconds. Display
will read "tS". Release button.
B. Press Reset button for 1 second. Display will read
"P01".
C. Press Heating buttons to scroll parameter list. Press
DHW buttons to view or change a parameter. Set
three (3) parameters "P01", "P02" and "P23" as
shown in Table 1 below and Figure 4.
Table - 1
tS Menu
CCB-150
P01
Gas Type
P02
Boiler Type
1
External
P23
CH Pump
3
Control
To access Configuration menu:
A. Press (DHW) + and - , hold both buttons for 10
seconds; "b01" appears and flashes.
B. Press Heating buttons to scroll Configuration list.
Press DHW buttons to view or change a setting.
C. Change only the Configuration "b01" per Table 2.
Remaining parameters are factory defaulted to the
correct value, verify value. See Table 3.
D. Select proper size, press and hold (DHW) + and -,
both buttons for 10 seconds to exit, or turn power
off then on, or wait two (2) minutes for auto exit.
15.
Replace jacket casing.
16.
Verify proper operation by following START UP
PROCEDURE in Installation, Operation & Maintenance
Manual.
Table - 2
Parameter
b01
Curve Selection
b01
b01
b01
b01
Table - 3
Configuration Menu
b01
Power Selection
Offset max.
b02
setpoint air signal
b03
Burner selection
Offset min.
b04
setpoint air signal
CHB-100
CHB-130
0 = Natural Gas
1 = LP Gas
2
2
3
3
Description
Setting
Default = 2
CHB-100
0
CHB-130
1
CHB-150
2
CCB-150
2
CCB-150 CHB-130 CHB-100 CHB-150
2
1
0
0
0
0
40
40
Figure 4
CHB-150
2
3
0
2
0
0
0
0
40
40
46
CH
DHW
REF #615000134, REV C [02/2016]
PN 3541F682

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

CcbChb 150Chb 100Chb 130Ccb 150

Table of Contents