Installation
Fuse
F12
F13
F15
F16
F900,F901,F902
F00
Table 3.2

Mechanical Installation

Lifting
Check the weight of unit to determine the safety of the lifting method. Ensure that the lifting device is suitable
for the task. If necessary, plan for a hoist, crane or forklift with appropriate rating to move the units.
Hoist or Overhead Lift
Use solid steel spreader bar for lifting. Slide spreader bar through two (2) lifting rings on drive. Lifting
rings are 19 mm (0.75 in) in diameter (see previous table).
Connect spreader bar to a hoist or other lifting device.
Lift unit slightly using lifting rings with weight distributed evenly.
Remove skid and other supports from under drive.
For floor mounting applications, a floor mounting kit is available from Trane specifically designed to
anchor drive to floor.
Forklift
Only a competent lift operator with additional support personnel should attempt moving unit.
Carefully position forklift and ensure stability prior to lift.
14
Manufacturer
Ferraz-Shawmut
Ferraz-Shawmut
Bussmann
Bussmann
Ferraz-Shawmut
...
Part Number/Size
500V FA 5 A
500V FA 10 A
LPJ-25SP
LPJ-25SP
500V FA 4 A
600 VAC, 120 A, Class CC
TR200 Option Panel Operating Instructions