2.1 INTRODUCTION

The information in this section provides a guide to the operation of the Benchmark Boiler using
the C-More Controller mounted on the front of the unit. It is imperative that the initial startup of
this unit be performed by factory trained personnel. Operation prior to initial startup by factory
trained personnel may void the equipment warranty. In addition, the following WARNINGS and
CAUTIONS must be observed at all times.
WARNING!
ELECTRICAL VOLTAGES IN THIS SYSTEM INCLUDE 220 VAC (BMK 750 – 2000)
and 220 or 380 VAC (BMK 2500/3000) and 24 volts AC. It must be serviced only by
factory certified service technicians.
DO NOT ATTEMPT TO DRY FIRE THE UNIT. Starting the unit without a full water level
can seriously damage the unit and may result in injury to personnel or property damage.
This situation will void any warranty.
CAUTION!
All of the installation procedures in the Benchmark 750 – 3000 Boiler Installation and Startup
Guide, OMM-0127 (GF-205-K) must be completed before attempting to start the unit.
OMM-0128_0C
GF-206-K
AERCO International, Inc. • 100 Oritani Dr. • Blauvelt, NY 10913
Ph.: 800-526-0288
Page 11 of 146
11/29/2017

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents