5 Commissioning

5.1 Before you switch on

The controllers are factory-set to drive a corresponding four-pole
standard motor with 230/400V , 50Hz. Further settings are not
necessary.
Only a few settings via the 8201 BB operating module or a fieldbus
module are necessary to adapt your drive to your application. The
steps required are summarized in chapter 5.3 and in chapter 5.4.
Prior to initial switch-on of the controller, check the wiring for
completeness, short-circuit, and earth fault:
-
Power connection:
- Via terminals L1/N - 820X.
- Alternatively via terminals +UG, -UG (DC-group drive)
-
Control terminals:
- Reference potential for the control terminals is terminal 39.
- Controller enable: terminal 28
- Selection of direction of rotation: terminal E3 or E4
- External setpoint selection: terminals 8, 9
- Check jumper position! Factpr settomg: 0 - 10 V
(see page 4-10).
- During operation with an internal voltage supply via terminal
20, bride the terminals 7 and 39.