CHAPTER 9

9.1 Introduction

Nokia RoofTop™ Wireless Router Installation Guide

Post installation testing

It is necessary to ensure that the system is working correctly after full
wireless router, Network/ Power Unit installations and PC configuration
are complete.
To carry out the test, follow the procedure shown below.

9.1.1 Functional testing

Ensure that the router functions correctly by carrying out the following:
1.
Ensure that the NPU is inserted properly into the AC-outlet. The
LEDs flash three times to indicate that the router is functioning
correctly.
2. Turn on the customer's PC. Wait for 3-5 minutes to allow the
router to anchor to the network.
3.
Check the LEDs to indicate active internet connection, according to
Chapter 7- Indoor installation.
55