Assembly Instructions / Power2 800-M
5
Installing the high-pressure stage
5.2

Assembly procedure

Air suction branch with bellows installed
If the high-pressure stage is transported with the air suction branch and bel-
lows installed, the bellows may be damaged.
CAUTION
Transport and put down air suction branch together with bellows separate-
ly.
Figure 9: Installing the high-pressure stage
Attach one lifting gear to the two suspension points of the bearing casing and one lifting
gear to the support.
Check that the orifices specified for the high-pressure stage have been installed in both oil
supply pipes.
Check that the gaskets have been correctly fitted at the oil inlet and the oil outlet in the
bracket.
Check that the sleeves of the bearing casing fixing screws have been correctly fitted.
Align the high-pressure stage on the engine.
Tighten fixing elements at foot and support (see Table 11).
Connect the cable connector to the speed sensor.
Install air suction branch together with bellows.
Secure all gas, air, water and oil pipes.
© Copyright 2016 ABB. All rights reserved.
HZTL455311P0010
Page 17 / 21
Revision -
March 2016

Advertisement

Table of Contents
loading

This manual is also suitable for:

Power2 850-m

Table of Contents