Installation and Setup Guide
Unpack the system
Install the rack brackets
Bracket hardware
EMC CloudBoost 100 2.0 Installation and Setup Guide
12
Procedure
1. Open the "Open Me First" box.
2. Remove the accessories and rack-mount kit from the shipping packages.
3. Remove the controller and bezel from the shipping packages.
CloudBoost 100 systems are installed into racks using the rack bracket hardware.
The rack-mounting kit is compatible with racks that have front-to-rear post spacing
between 18 inches and 36 inches. The kit will fit the following types of mounting
holes:
7.1 mm round holes
l
.375 inch / 9.2 mm square holes
l
M5, M6, 12-24, and 10-32 threaded holes
l
The kit includes the following items:
Two bracket assemblies, one marked for the left (L) side and one marked for the
l
right (R) side of the rack.
Figure 9 Bracket assembly
1. Front.
2. Back.