4 Wall / Wall Bracket
•
Inspect that there is no play between the wall and the
bracket.
•
Inspect the fixing between the rail and the wall bracket.
5 Upright Support
•
Make sure that there is no play between the fixing points
in the wall and the upright support.
•
Inspect the fixing between the wall and the upright
support.
•
Inspect the floor for damage/deflection around the
bottom of the upright support.
6 Primary rail, ( straight rail, traverse )
•
Make sure there are at least two fixings per rail.
•
Inspect that joint gap is max 2 mm / 0,08 inch. (A)
•
Make sure that the rail joint is supported by a fixing or a
proper joint section.
7 Secondary Rail
•
Inspect that the drawing affect in the system is
acceptable, by placing a force (F) on one side.
The secondary rail (B) should then run freely.
8 Traverse Carriage
•
Inspect that the carriers are functioning correctly with-
out exercise. Listen for abnormal sounds from movable
parts.
ServiceManual Likorall™ overhead lift (3EN200405 Rev 10)
Periodic Inspection Rail System, 3EN111001 Rev. 10
Likorall™
Instructions for inspection points
(A)
(B)
116
6.2
F
www.liko.com