Page 1
Instruction Manual LIQ-MAN-245 Rev. E June 2017 Rosemount Toroidal Flow-Through Conductivity Sensor...
Page 2
Addition of section 1.7 on page 5 3/12 Update pages 12 and 16 01/14 The manual has been reformatted to reflect the Emerson documentation style and updated to reflect any changes in the product offering. Wiring diagrams were also added under Section 1.
Page 3
Essential Instructions Read this page before proceeding Rosemount designs, manufactures, and tests its products to meet many national and international standards. Because these instruments are sophisticated technical products, you must properly install, use, and maintain them to ensure they continue to operate within their normal specifications. The following instructions must be adhered to and integrated into your safety program when installing, using, and maintaining Rosemount products.
Instruction Manual 245 Sensor LIQ-MAN-245 June 2017 Section 1: 245 Sensor Features and Applications The 245 Sanitary Flow-Through Toroidal Conductivity Sensor is intended for use in the pharmaceutical, biopharmaceutical, and food and beverage industries where a conductivity sensor that does not obstruct the process flow is required. The sensor consists of two toroids surrounding a PEEK liner through which the liquid flows.
245 Sensor Instruction Manual June 2017 LIQ-MAN-245 Figure 1-1 Sanitary Flow-Through Toroidal Conductivity Sensor Ordering Information The 245 Sanitary Flow-Through Sensor is configurable to meet the needs of many applications and installations. A NEMA 7D junction box is also included. Compatible instruments include Rosemount 1056, 56, 5081T, and 1066-T.
Instruction Manual 245 Sensor LIQ-MAN-245 June 2017 Installation Before starting installation, determine whether the analyzer/transmitter will be calibrated at the bench or on-line. If bench calibration is to be performed, wiring instructions can be found at the end of this section and calibration procedures can be found in Section 1.5. Installation of the 245 Flow Through Sensor is similar to installation of a section of pipe.
245 Sensor Instruction Manual June 2017 LIQ-MAN-245 Figure 1-2 245 Junction Box with RTD Diagram (use of optional kit PN 24086-00 is recommended) Calibration Before starting the calibration, enter the nominal cell constant into the analyzer. See Table 1-1. The accuracy of the nominal cell constant is probably no better than 10%. For greater accuracy, calibrate the sensor.
Instruction Manual 245 Sensor LIQ-MAN-245 June 2017 1.5.2 In-line calibration against a laboratory measurement 1. Install the sensor in the process piping. 2. Obtain and calibrate a laboratory conductivity meter and sensor capable of measuring the conductivity of the process liquid. 3.
Instruction Manual 245 Sensor LIQ-MAN-245 June 2017 Figure1-8 Wiring extension cable to Xmt-T (Pipe/Wall Mount) Figure1-9 Wiring extension cable to 1066-T Figure 1-10 Wiring extension Cable to 5081T RCV B SENSE RCV A RTD IN RSHLD SHLD DRV B DRV A DSHLD CLEAR CLEAR SHIELD...
Page 14
245 Sensor Instruction Manual June 2017 LIQ-MAN-245 This page left blank intentionally 245 Sensor...
Instruction Manual Troubleshooting LIQ-MAN-245 June 2017 Section 2: Troubleshooting Troubleshooting To check the toroids, recall the data obtained during the Calibration Verification Process (see Section 1.6). With the sensor empty of process fluids (preferably also clean and dry), reapply the resistance to the yellow Cal Loop wires in the junction box. The reading should be within + 20% of its original value.