Configuration

About this section

This section guides you in the configuration tasks required before you can start using
the DNP OPC Server. For information on the IEC 61850 data modeling, refer to COM600
User's Manual.
Start Station Automation Builder 600 (later referred to as SAB600). Then either open a
project where at least one DNP OPC server is present, or where a new DNP OPC server
will be added. You can also open and name a new project to include one or more DNP
OPC servers.
1. Select File > Open/Manage Project....
2. In the Open/Manage Project dialog, select the required location for the project:
Projects on my computer.
Projects on network.
3. Select New Project on the left.
Enter a Project Name. The Description is optional.
4. Click Create.
5. Click Open Project.

Overview of configuration

Before you can start using the DNP OPC Server, build and configure an object tree in
Station Automation Builder 600 (SAB600) to define the Communication structure within
the Gateway object. An object tree contains the following branches:
Gateway
DNP Serial OPC Server
DNP Serial Channel
Logical Device objects
Logical Node objects
Data objects
After you have added the necessary objects to the object tree in the communication
structure, configure them.
The configuration work can basically be divided into two separate tasks:
1. building the object tree, and
2. configuring object properties.
First, build an object tree. This is done by adding objects to the object tree, see
3.3.1, General information about building object tree.