7.5.9
Designation of the earth connec-
tion
Safety labels
fig.16:

Designation of the earth connection

Importance of the labels
Ensure that the product is properly grounded before
start-up. Connect the earth connection. The neces-
sary mounting hardware and cables are not included
in scope of supply.
7.6

Process flow diagram

fig.17:
Process flow diagram Grasso SP1, M-series
1
Suction side
2
Compressor
3
Oil separator
4
Pressure side
GEA Refrigeration Germany GmbH | P_261511_1 | Generated 01.04.2015
See general assembly drawing for the position of the
earth connections.
Hint!
The cross-section of the ground wire
must be at least 10 mm². Alternatively,
two separately installed and separately
connected ground wire must be used,
ensuring the minimum cross-section
in the sum.