The switch "S1" indicated in Fig. 15 should be placed to position "PAR" (default
position) in order to configure the inverter in parallel mode (default set-up).
After switching the Aurora inverter to parallel mode configuration, the front panel
should be reinstalled (apply 13.2 in-lbs of torque to each of the 4 screws). After the
front panel is secured, it is possible to begin the START-UP procedure. (see
section 4).
3.3.7

Connection to the AC GRID

WARNING: Before performing any operation on the Switch Box power
input or on the Inverter, ALWAYS perform the disconnection procedure as
explained in section 3.3.1 or 3.3.2 of this manual.
Fig. 16 - Parallel Connection
Page 43 of 104

Hide quick links:

Advertisement

Table of Contents
loading
Need help?

Need help?

Do you have a question about the aurora and is the answer not in the manual?

Subscribe to Our Youtube Channel

Table of Contents

Save PDF