2.7 Installing and uninstalling the cooling system
Installing the cooling system:
a) Place the machine in the vertical position,
b) Slide the drive and the slider (1) up using lever (2),
c) Coolant bracket (7) with cooling unit (6) on screws (8) located to the side of the slider,
d) Connect the cooling conduit ending (3) with the coolant coupling (4) found in the cooling
ring (5).
Before starting the machine:
Remove the bottle's cap,
Fill it with cooling lubricant,
Replace bottle cap.
After fulfilling the above actions and making sure, that the system has been appropriately
fixed, and the cooling conduit (3) is placed correctly on the coolant coupling (4), the bottle
cap should be loosened by 1/3 of a turn in order to deaereate it, turn on the valve (9), so that
liquid travels to the hose, after which the machine can be started (see II pt. 3)
After ending work, one must remember to tighten the bottle cap and turn off the valve
(9) (to prevent liquid from leaking during the time that the machine is not being used) and
uninstall the cooling system (6) before placing the machine in the box.
Uninstalling the cooling system:
a) Place the machine in the vertical position,
b) Slide the drive and the slider (1) up using lever (2),
c) Disconnect the cooling conduit ending (3) and the coolant coupling (4) found in the
cooling ring (5).
d) Take off the cooling system.