Installing the Power Cord

The POWER port on the unit is a standard, grounded, three-prong connector. The unit
has no power switch.
Figure 1. Hotwire 8300 Endpoint Back Panel
Procedure
1. Insert the power cord's receptacle into the POWER jack.
2. Plug the other end of the power cord into a grounded power outlet.
3. Check the LEDs.
When power is applied to the unit, the front panel indicators flash for approximately 10 to
15 seconds as the unit initializes itself. The green POWER LED on the front panel
remains on as long as the unit receives power. If the indicator does not light up, check
the power connections and the primary circuit breaker.