Verifying The Installation - HP 5500 HI Series Installation Manual

Hide thumbs Also See for 5500 HI Series:
Table of Contents

Advertisement

Wear an ESD-preventive wrist strap and make sure it makes good skin contact and is well
1.
grounded. Then unpack the dedicated SFP+ cable.
Hold the connector at one end of the cable, with the pull latch on top.
2.
Orient the connector with the port and insert it into the port.
3.
Removing a CX4/SFP+ cable
To remove a CX4 or SFP+ cable from a port on a CX4/SFP+ interface card:
Wear an ESD-preventive wrist strap and make sure it makes good skin contact and is well
1.
grounded.
Hold the cable connector and pull the pull latch of the connector to remove the cable from the
2.
switch.

Verifying the installation

After you complete the installation, verify that:
There is enough space for heat dissipation around the switch, and the rack or workbench is stable.
The grounding cable is securely connected.
The correct power source is used.
The power cords are properly connected.
All the interface cables are cabled indoors. If any cable is routed outdoors, verify that the socket
strip with lightning protection has been properly connected.
31