Heating System Inspection And Maintenance; General Notes; Preparing The Boiler For Cleaning - Buderus Logano GE434 Maintenance Instructions Manual

Table of Contents

Advertisement

Heating system inspection and maintenance

8
Heating system inspection and maintenance
8.1

General notes

Offer an annual inspection and maintenance contract
(depending on requirements) to your customer. You can
check in Chapter 8.8 "Inspection and maintenance
reports", page 45 what is required for such contracts.
PLEASE NOTE
You may order spare parts from the
Buderus spare parts catalogue.
8.2

Preparing the boiler for cleaning

! Shut down the heating system (see Chapter 7
"Shutting down the heating system", page 34).
RISK TO LIFE
from electric shock when the heating
system is open.
WARNING!
! Before you open the heating system:
Isolate the heating system with the
heating system emergency stop switch
or by extracting the mains fuse.
! Safeguard the heating system against
unintentional re-connection.
! Remove the side panels from the boiler, the bottoms
of which are secured with self-tapping screws.
RISK TO LIFE
through the explosion of volatile gases.
! Work on gas components must only be
WARNING!
carried out by qualified and authorised
personnel.
We reserve the right to make any changes due to technical modifications.
Commissioning and maintenance instructions Logano GE434 Gas-fired special boiler • Issue 02/2003
Buderus Heiztechnik GmbH • http://www.heiztechnik.buderus.de
8
35

Hide quick links:

Advertisement

Table of Contents
loading

Table of Contents