Installation Procedures

Prepare the Site

Before you begin installing the hub, prepare the installation site. Make sure the
site meets the operating environment requirements of the equipment.
Characteristic
Requirement
Temperature
Ambient temperature between 0
(32
direct sunlight, warm air exhausts, or heaters.
Humidity
90% maximum relative humidity, noncondensing.
Ventilation
Minimum 2 inches (5.08 cm) on all sides for cooling.
Operating conditions
At least 6 feet (1.83 m) to nearest source of electromagnetic
Service access
Minimum 12 inches (19.68 cm) front and back for service
Power
Adequate power source within 6 feet (1.83 m).
Wiring hardware
Wiring hardware, such as punchdown blocks or patch panels,

Install the Hub

Install the Hub on a Flat Surface
If installing the hub on a flat surface such as a tabletop, make sure the bottom of
the chassis is clean and dry.
To install the hub on a flat surface:
1. Set the hub on a table or shelf so that it has at least 2 inches (5 cm) of
space on all sides.
2. Connect the power cord(s) first to the power entry receptacle on the
hub rear panel and then to the wall.
Model DS104/106/108/116 Dual Speed Hub Installation Guide
G
G
and 104
F). No nearby heat sources such as
Adequate airflow in room or wiring closet.
noise (such as photocopy machine or arc welder).
access and maintenance.
Front and back clearance for cables and wiring hardware such
as punchdown blocks.
complete before installing the hub.
G
G
and 40
C

Advertisement

Table of Contents
loading

This manual is also suitable for:

Ds 106Ds 108Ds 116

Table of Contents