4 Pipe and ventilation connections

General pipe connections

Pipe installation must be carried out in accordance with
current norms and directives.
The system requires a low-temperature design of the
radiator circuit. At lowest dimensioned outdoor tem-
perature (DUT) the highest recommended temperat-
ures are 55 °C on the flow line and 45 °C on the return
line.
NOTE
The pipe system needs to be flushed out be-
fore the heat pump is connected so that any
debris cannot damage component parts.
NOTE
This installation is subject to building regula-
tion approval, notify the local Authority of in-
tention to install.
NOTE
Use only manufacturer's recommended re-
placement parts.
Waste water from the collection tray at the evaporator
and from the safety valve is led by a non-pressurised
overflow pipe to the drain so that hot water cannot
cause damage. Likewise should the discharge pipes
Valve outlet size
G1/2
G1/2
G1/2
<G3>/4
<G3>/4
<G3>/4
G1
G1
G1
Hard water areas
Usually, there should not be a problem in installing
F370 in areas of hard water as the operating temperat-
ure is 50-60 °C.
Cleaning the climate system
When the water heater and the climate system have
been filled with water, F370 must operate at maximum
12
Chapter 4 |
Pipe and ventilation connections
Minimum size of dis-
Minimum size of dis-
charge pipe
charge pipe from
tundish
15 mm
22 mm
15 mm
28 mm
15 mm
35 mm
22 mm
28 mm
22 mm
35 mm
22 mm
42 mm
28 mm
35 mm
28 mm
42 mm
28 mm
54 mm
(tundishes), drain valves and motorised valves be posi-
tioned clearly away from any electrical components.
This is the only thing the non-pressurised overflow pipe
may be used for. Even overflow pipes from tundish
connected to the expansion relief valve must be con-
nected to the drain in the same way.
Please note that the connection of the T&P-valve should
not be used for any other purpose.
Valves may not be positioned between the expansion
valve and the vessel.
Discharge pipes from tundishes shall have av vertical
section of pipe at least 300 mm long, before any elbows
or bends in the pipework (see following picture).
Metal discharge pipe from
temperature relief valve to tundish.
Safety device
500 mm maximum
(e.g. temperature
relief valve).
300 mm
minimum
Metal discharge pipe from tundish,
with continous fall.
Maximum resistance
allowed, expressed
as a lenght of
straight pipe (i.e. no
elbows or bends)
up to 9 m
up to 18 m
up to 27 m
up to 9 m
up to 18 m
up to 27 m
up to 9 m
up to 18 m
up to 27 m
normal temperature for at least one hour. Thereafter
the system must be drained of water and refilled. See
section Service actions on page 50.
Before installing the heat pump in an existing system,
it is important that the system is properly flushed
through.
Even if the heat pump is to be installed in a new system,
the heat pump and system should be flushed.
Tundish
Discharge below
fixed grating.
Fixed grating
Trapped gulley
Possible wall
Resistance created by
each elbow or bend
0.8 mm
1.0 mm
1.4 mm
1.0 mm
1.4 mm
1.7 mm
1.4 mm
1.7 mm
2.3 mm