Component Access; Fan Pressure Test - Worcester 29CDi Classic Installation, Commissioning And Servicing Instructions

Greenstar cdi classic erp wall hung rsf gas fired condensing combination boiler
Hide thumbs Also See for 29CDi Classic:
Table of Contents

Advertisement

6.1.2

COMPONENT ACCESS

Removing outer case
1. Remove bottom panel by pulling it forward and off.
2. Undo but do not remove the two screws (A) securing boiler casing at
the bottom of the appliance.
3. Pull upwards to release the clip (B) on top of the boiler.
4. Pull case forward and remove.
2.
A
Fig. 61 Removing outer case
2. Adjusting boiler control to service position
1. Slide down the white plastic clip securing the control panel.
2. Pull the control panel forward until it comes to rest in service
position.
6 720 815 725 (2015/05)
1.
Fig. 62 Controls to service position
6.1.3
3.
SET THE BOILER TO MAXIMUM
B
4.
A
L
K
J
I
Fig. 63 Control panel
[A]
ON/OFF button
[B]
Cover or optional plug-in controller
[C]
Display
[D]
System pressure gauge
[E]
Reset button
[F]
ECO button
[G]
Holiday button
[H]
DHW temperature control
[I]
Central heating control
[J]
Performance test button
[K]
Service button
[L]
Burner indicator (green)
[M]
ON/OFF and fault indicator (blue)
1.

FAN PRESSURE TEST

This test is to determine if the heat cell requires cleaning/
attention
▶ When running in the Performance test mode, the
boiler will operate only the Central Heating circuit.
▶ The heating output can be limited to any level
between minimum and maximum rated heat output
to suit a specific requirement.
Even when the heat output is limited, full heat output
is still available for domestic hot water.
B
3
4
5
2
1
6
max
M
SERVICING AND SPARES
2.
6 720 815 725-08.1O
C
2
1
1
3
0
4
bar
D
reset
eco
E
F
3
4
e
2
G
1
6
min
max
H
6720647361-23.2Wo
39