Electrical connections

Routing of the connecting cables

2.
1.
5.
6.
8.
5862130G - page 11 (Black)
Screen angle and frequency: 45.0000, <default>
(continued)
¨ Safety instruction:
When running and securing the connecting cables on site, take care to ensure
that the maximum permissible temperatures of the cables are not exceeded.
3.
7.
1. Secure the cables coming out of
the wall to the transverse bracket
with cable ties.
2. Pull the cables forward between
the support arm and the control
unit.
Please note:
It is essential to route the cables
as shown in the drawing to guar
antee the correct freedom of
movement of the control unit.
Take care to avoid kinking the cap
illaries of the manometer.
3. The cables below the control unit
should be secured together with
cable ties.
Please note:
Do not secure cables in the vicin
ity of the control unit to the trans
verse bracket.
4. Break off the necessary number of
tabs to provide openings in the
case for the external cables to be
connected (see page 10).
5. Fit the necessary bushings.
4.
6. Fit the bottom parts of the strain
relief clamps at the corresponding
bushings.
7. Run the cables into the control
case through the corresponding
bushings.
8. Screw on the top parts of the strain
relief clamps.
Control unit
11