Snom M700 Deployment Manual page 10

Hide thumbs Also See for M700:
Table of Contents

Advertisement

 
a) The Synchronisation chain must always overlap with other Base stations in order to latch each 
other. 
b) In this illustration Base station #39 is the Sync Master, RPN 00 (Radio Fixed Part Number) 
c) A maximum of 7 sync levels (Including the master bases) can be used in a deployment. 
d) The other slave base stations or repeaters are connected to the Sync Master through the 
synchronisation chain. 
e) If one of the base or repeater units in the sync chain is broken or not working, then the units that 
follow the non‐working device are cut off from the sync chain, and air‐interface synchronization 
can be lost. When the air interface synchronization is lost handover between the two clusters is 
not possible. 
 
 
The sync level concept is illustrated below, where bases #08 and #02 are at sync level 1, and BS#03 is 
at level 2. 
 
 
 