7. OPERATION TEST
7-1 Pre-check points
All wiring are connected correctly.
The motor power output is fit inverter's specification.
Wire clips or screws are not left in the unit.
Screw-type terminals are screwed tightly.
The cover of inverter's is fixed tightly.
7-2 Cautions for operating test
Avoid damaging the machine, please do the operation
test by no load.
Before input power, check the voltage and wiring are cor-
rect.
After input power, any unusual noise, smoke or smell
please turn OFF power immediately.
Confirm the following list before operation :
Check motor operation smoothly.
Correct motor operating direction.
No unusual vibration happened.
Check acceleration and deceleration speed is smoothly.
Load current is below the rated current.
Correct operational pad display indicator.
19