Download Print this page

Electrical Supply - REMEHA 350 Technical Information

Atmospheric gas boiler with reduced nox emission 64 - 174 kw
Hide thumbs Also See for 350:

Advertisement

10. COMMISSIONING
Note:
Commissioning to only be carried out by a qualifi ed
engineer with the relevant training and certifi cation i.e.
Acops-Corgi and a commissioning data sheet completed
on site for issue of owner.
10.1 Technical information
Control box: Satronic DKG972.
Main supply: 230 V-50 Hz.
Minimum ionisation current: 3 µA.
Reaction time fl ame protection: 1 sec.
Safety time: < 10 sec.
Maximum ambient temperature: 60°C.
Injector size pilot burner: Ø 0.5 mm.
Injector size main burner: Ø 4.0 mm.
Burner pressure full load: 14.0 mbar (100%).
Burner pressure part load: 5.0 mbar (60%).
Start repetition: 5x.
Warning:
Control box operates on a neutral/phase supply.
10.2 Commissioning the boiler
1. Check gas connections.
2. Check electrical supply (L/N and earth).
3. Check water connections and if installation is fi lled.
4. Switch on circulation pump and check rotation
direction.
5. Open main gas cock (release air in gas pipe work).
6. Switch on electrical supply.
7. Set the control thermostats at about 85°C.
8. After a waiting time of about 3 seconds you will get
ignition. At a minimum ionisation current of 3 µAmp
the safety gas valve will open. The boiler is on.
9. Let the boiler run for a couple of minutes to get rid
of air in the gas pipe.
10. Set the correct burner pressure.
11. Check the thermostats for correct operation.
12. Check the fl ame protection, by starting the ionisation
probe disconnected.
13. Send the commissioning reports to Broag.
10.3 Switching off the boiler
1. Set boiler controls to off.
2. Allow system to cool.
3. Switch off the electrical supply.
4. Turn off the gas cock.
10
Remeha Gas 350

Hide quick links:

Advertisement

loading