2.10.3 Checks After Start-up

After initial start-up of the system, normal operation should be tested. At the minimum, the following tests should be
performed as applicable to your installation:
Emergency power off (EPO) test.
Remote emergency power off (REPO) test (if applicable).
Inverter start and stop.
Battery transfer test.
Maintenance bypass procedure.
2.11

Shutdown

Shutdown procedures in this section apply to the EPS 8000 UPS cabinet under normal, emergency, overload, and
maintenance conditions.

2.11.1 Emergency Shutdown Using EPO

CAUTION:
During an emergency situation, such as a fire in the computer or electrical room, the UPS and all downstream
devices can be instantly shut down by pressing the "emergency power off" (EPO) pushbutton on the front panel of
the UPS cabinet, or by pressing the "remote emergency power off" (REPO) optional pushbutton located within the
room.
The EPO or REPO pushbuttons should not be used for normal shutdown of the equipment; when activated, ground
paths may be broken (depending on installation) and sensitive loads attached to the UPS may lose safety ground
connection.
If the transfer conditions are not satisfied (bypass AC input
sources is out of tolerance) a forced transfer is required.
Refer to section 2.12 Forced Transfers.
Pressing the EPO disconnects the attached load. The
emergency power off (EPO) is to be used during emergency
situations only, where a hazard to personnel or equipment
exists, such as during a fire. DO NOT USE THE EPO TO
TURN THE UPS OFF; follow the procedures listed in
this section for turning the inverter on and off.
Operation
Users Manual
page 2 —15

Hide quick links:

Advertisement

Table of Contents
loading

This manual is also suitable for:

Eps 8000 ups

Table of Contents