Evacuating and Charging

Evacuating the tubing and the indoor unit

The outdoor unit is pre-charged with refrigerant R-22. The
indoor unit and the refrigerant connection tubing must be
evacuated as follows:
1.
Remove the 3 caps from the valves on the outdoor unit.
2.
Connect the center of the charging gauge to the
vacuum pump.
3.
Connect the charging gauge to the service port of the
3-way valve (See Figure 9).
4.
Start the pump and evacuate to -760 mm Hg (-29.9" Hg).
5.
Close the valve of the changing gauge and stop the
vacuum pump.
6.
On the outdoor unit, open both valves using a 4 mm
Allen wrench (See Figure 8).
Figure 8. 3-way Suction Valve on Outdoor Unit
Hex Socket
for 4 mm
Allen wrench
Service
Port
Figure 9 Evacuation Schematic
Indoor Unit
Liquid side
Gas side
Vacuum
Pump
Low
Press.

Additional charge

The refrigerant is pre-charged in the outdoor unit. If the tub-
ing length between the indoor and outdoor unit is no more
than 25 ft., then an additional charge after evacuation is not
necessary. If the tubing length is more than 25 ft., use addi-
tional R-22 as indicated in Table 7.
IM 820
Refrigerant
Tubing
Flare Nut
Outdoor Unit
3-way Valve
Outdoor Unit
Discharge Valve
Close
Suction Valve
Close
High
Press.
Table 7: Additional R-22 ounces per foot of tubing
(when tubing length is more than 25 ft.) and maximum
tubing length.
Model
20D
25D
30D
40D
50D
20DR
25DR
30DR
40DR
50DR

Charge operation

This operation must be done by weighing the R-22 being
added thru the service port on the 3-way suction valve.
See Table 7 and Figure 10.
1.
Remove the service port cap.
2.
Connect the low pressure side of the charging gauge to
the suction service port center of the cylinder tank and
close the high pressure side of the gauge. Purge the air
from the service hose (See Figure 10).
3.
Start the air conditioner unit.
4.
Open the gas cylinder and low pressure charging valve.
5.
When the required refrigerant quantity is pumped into
the unit, close the low pressure side and the gas cylinder
valve.
6.
Disconnect the service hose from service port. Put back
the service port cap.
Figure 10. Charging Schematic
Indoor Unit
Liquid side
Gas side
Low
High
Press.
Press.
Oz. Per ft.
Max. Length
.16
49'
.40
49'
.53
115'
.55
115'
.55
115'
.16
49'
.50
49'
.53
115'
.55
115'
.55
115'
Outdoor Unit
Discharge Valve
Suction Valve
Page 17