Initial commissioning
Setting up a payment system
This option allows you to set up an ex-
isting payment system.
If you do not wish to set up a payment
system:
No payment
system
Payment
Programme
system
control
Touch the
No payment system
control.
Continue reading from "Completing
the commissioning process" under
"Initial commissioning".
If you wish to set up a payment system:
These settings can only be changed dur-
ing the initial commissioning process. If
you wish to change the settings after
the commissioning process, please con-
tact Miele Service.
Touch the sensor control re-
peatedly until the setting you require
appears.
Touch the sensor control for the set-
ting you want.
The process for setting up a payment
system is described under "Payment
systems" in the chapter "Supervisor
level".
Completing the commissioning
process
The commissioning process is com-
pleted by running the
programme through to the end.
26
sensor
Commissioning
The programme takes 20 minutes to
complete and must run through to the
end.
If the mains supply is interrupted (or
the appliance is shut down by press-
ing before or during the
programme, commissioning will
sioning
be cancelled. If this happens, the initial
commissioning process must be re-
peated.
To complete the
commissioning,
start the
Information
"Commissioning"
programme
without laundry
Confirm with the OK sensor control.
Commissioning
0:20
h
Touch the flashing Start/Stop sensor
control.
When
Commissioning Finish
up, switch the tumble dryer off briefly
and then switch it back on again.
Initial commissioning is complete and
the tumble dryer is ready for drying.
Commis-
OK
0:20
lights
h