Start-Up

Table 13. Initial start-up readiness checklist (continued)
Start-Up Readiness Dimension
☐ ☐
Check the box if high voltage wiring is installed, tested, and functional.
Check the box if all water, refrigeration, and electrical connections between chiller modules are completed.
Check the box if all control wiring between modular chillers is installed, tested, and functional.
Check the box if control wiring is complete, including any additional remote interface panel or special-purpose wiring.
Check the box if all responsible installing contractors and sub-contractors have been notified to have representatives available on site to provide technical
support for the initial start-up procedure.
Check the box if full load will be available for chiller on the initial start-up date.
Touchscreen Interface Panel: Record version and date of the software loaded into the touchscreen interface panel:
Version: ____________________________________ Date: ________________
Note: To view the software version, from the home screen, press the software button on the System Control screen.
Start-Up
As part of a continuous commitment to quality, initial start-
up of this chiller must be done by Trane.
56
ARTC-SVX008A-EN