Table 13. Initial start-up readiness checklist
Start-Up Readiness Dimension
☐ ☐
Describe voltage service:
☐ Fused disconnect
☐ Non-fused disconnect
☐ 50 Hz
☐ 60 Hz
Record rated power supply: __________volts_______ phase
Circuit breaker rating: _______
Record supply voltage on chiller nameplate: _________________
Record power supply voltage to ground: L-1= _______, L-2 = _______, L-3 = _______
Record voltage between each phase: L-1 to L-2 = ______, L-2 to L-3 = ______, L-1 to L-3 = ______
☐ Agrees with nameplate values?
☐ Voltages must be within 2%.
Check the box if all electrical connections inside the power distribution panel are tight.
Check the box if all electrical connections inside each module electrical and control panel are tight. Confirm all components inside each module are
securely mounted and have not shifted during shipment.
Record the control voltage between TB-1-1 and TB-2-1: ________
Check the box if chiller system includes any remote panels (city water switchover, remote control panel, or customer supplied control devices). If so,
voltage drops are likely to occur. Measure and record all control voltages:
List devices: Voltage 1=_____________________ Voltage 2=_____________________ Voltage 3=___________________
Check the box if there are any field-supplied wiring junction boxes located between the chiller and any remote panels.
Check the box if there are any splices made in the field-supplied wiring junction boxes.
Check the box if there are any customer-supplied devices connected to the chiller wiring.
List devices: ______________________________________________________________________________________
Check the box if there are any Trane remote devices connected to the chiller wiring.
Check the box if voltage drops are detected.
Check the box if the appropriate water/glycol mixture has been added to the chiller.
Check the box if all chiller modules are installed with minimum clearances available from all sides.
Check the box if refrigeration gauges are indicating equal refrigerant pressures.
Check the box if chilled water lines from chiller to customer's equipment are permanently connected.
Check the box if chilled water lines have been flushed clean of mud, slag, and other construction debris.
Check the box if all chilled water line filters and strainers are clean.
Check the box if chilled water lines have been leak tested according to pre-start-up instructions.
Check the box if chiller reservoir (if included) is at operating level with correct water/glycol mixture.