5-13. Installing Gas Supply

.
DO NOT use Argon/Mixed gas regulator/flowmeter
with CO
shielding gas. See Parts List for optional
2
CO
gas regulator/flowmeter and hose.
2
Tools Needed:
5/8, 1-1/8 in.
6
Feedhead Pressure Assembly Open
Feedhead Pressure Assembly Closed
OM-264761 Page 22
.
A complete Parts List is available on-line at www.MillerWelds.com
4
7
5
1
2
3
Argon Gas Or
Mixed Gas
8
9
CO
Gas
2
270 208-B / Ref. 247 832-A / Ref. 267 807-A / Ref. 267 805-A
Obtain gas cylinder and chain to
running gear,
wall,
or
other
stationary support so cylinder
cannot fall and break off valve.
1
Cap
2
Cylinder Valve
Remove cap, stand to side of valve,
and open valve slightly. Gas flow
blows dust and dirt from valve.
Close valve.
3
Cylinder
4
Regulator/Flowmeter
Install so face is vertical.
5
Regulator/Flowmeter Gas
Hose Connection
6
Welding Power Source Gas
Hose Connection
Connect
supplied
gas
hose
between regulator/flowmeter gas
hose connection, and fitting on rear
of welding power source.
7
Flow Adjust
Flow rate should be set when gas is
flowing through welding power
source and welding gun. Open
feedhead pressure assembly so
that wire will not feed. Press gun
trigger to start gas flow.
Typical flow rate is 20 cfh (cubic
feet per hour). Check wire
manufacturer's recommended
flow rate.
8
CO
Adapter (Customer
2
Supplied)
9
O-Ring (Customer Supplied)
Install adapter with O-ring between
regulator/flowmeter
and
CO
cylinder.
After flow is set, close feedhead
pressure assembly.