INSPECTION OF THE CONTROL PANEL
Check that the control panel is free of foreign objects.
Power supply unit with three-phase electrical current.
Phase unbalance should be less than 2% of average.
Turn on each fan to ensure proper rotation.
Turn on the water pump (if applicable) to make sure it is running.
After completing the inspection of the above installation points and ensuring that all elements of the unit are correct, the unit can be
powered up. Turn the switch on the CONTROL UNIT to the ON position to power the control unit with 24 volts.
START-UP
After powering up the controller, wait 5 minutes for the unit to be ready to operate.
The operating sequence will begin by checking all pre-programmed safety points on the unit. If all required conditions are correct, the
unit will be ready to start operations.
UNIT CONTROL
To start operations, turn the ON/OFF switch to the ON position.
After 6 seconds, the control will command the pump to start.
If water flow is detected in the piping, the internal sequence of the unit will start.
NOTE : After completing the inspection of the above installation points and making sure that all elements of the unit are
correct, the unit can be turned on. Turn the switch on the CONTROL UNIT to the ON position to power the control
panel with 24 volts.
UNIT CONTROL
ON / OFF
iom-cliv-cf-eng
• To start operations, turn the ON/OFF switch to the ON position.
• After 6 seconds, the control will command the pump to start.
• If water flow is detected in the piping, the internal sequence of the unit will start.
• On / Off
40
Startup and shutdown procedures